 | Dirt Work - Following is the recommended
guidelines for dirt work and site preparation for a concrete foundation, in
instances where drainage could be a problem - 95%
compaction of standard proctor, +/-
2% of optimum moisture content, Select fill should have PI of less than 20,
Lifts should be no deeper than 9". |